How to write a procedure to change coolant in a machine shop
Summary
A machine shop coolant changeover comes down to six steps: lock out, drain, clean, rinse, recharge at target concentration, then check and record. That order holds for water-mix coolants in single sumps and central systems. Take the cleaner, its dose and its circulation time from the supplier's own instruction, and write the lockout and SDS duties into the steps themselves.
Quaker Houghton's dump, clean and recharge guide runs a cleaner or coolant through the system and fluid lines for 8-24 hours, then a broad-spectrum biocide for 4-8 hours where it is needed (Quaker Houghton, 2019).
Dubois Chemicals circulates its cleaner at 2% for 1-8 hours in individual machines, depending on severity of soils, and for at least 2-4 hours in a central system (Dubois Chemicals, 2020).
Water-mix coolant concentration equals the refractometer reading multiplied by the product's own adjustment factor (UKLA, 2025).
HSE's sump cleaning sheet has the fresh coolant dipslide-tested about a week after refill and kept in use when it shows less than 10,000 CFU/ml (HSE MW3, 2021).
This procedure covers water-mix coolants. Straight oil systems need a different cleanout with a flushing oil or solvent. In addition, a large enclosed sump or underfloor tank may be a confined space that needs its own permit. The written procedure works inside the shop's own lockout program and does not replace it.
What must a coolant changeover procedure cover before the old coolant is drained?
The procedure has to settle safety, waste, timing and materials before anyone drains the old coolant, because every later step depends on those answers. Quaker Houghton recommends a short meeting of everyone involved to confirm that the waste route can take the old coolant plus the cleaner and rinse water, that filtration is ready for a higher dirt load, whether automatic lubrication stays on, and which electrical parts and gauging need protection (Quaker Houghton, 2019). The same guide has all Safety Data Sheets (SDS) for the cleaner, coolant and biocide reviewed at that meeting, with any special personal protective equipment (PPE) noted, since cleanout chemicals often run higher in pH than normal parts cleaners.
Lockout belongs in the same planning. In the US, OSHA 29 CFR 1910.147 lists cleaning of machines as servicing, and paragraph (c)(1) requires machines to be isolated from the energy source and rendered inoperative before servicing where unexpected start-up could cause injury (OSHA, 29 CFR 1910.147, 2026). When a supplier's technician does the work, paragraph (f)(2)(i) requires the on-site and outside employers to inform each other of their lockout or tagout procedures.
Put in the procedure the name of the person who owns each of these answers. Then state in one line why the coolant is being changed, such as dirty fluid, a leak or microbial growth.
How do you write the drain, clean and rinse steps of a coolant changeover?
Write these steps as numbered actions in the order the crew will do them, each with one quantity and the source it comes from. The sequence below draws on the Quaker Houghton guide, the HSE sump cleaning sheet and the UKLA good practice guide. Swap each value for the one in your supplier's instruction.
Remove parts from the machines, because cleaner contact can stain or rust them (Quaker Houghton, 2019).
Lock out the machine and coolant pump for every stage where hands or tools go into the sump, filters or conveyor. Follow the site procedure under OSHA 29 CFR 1910.147 and wear the PPE listed in each product's SDS.
Drain the old coolant, including areas below the main pump level, to the waste route agreed before the job.
Remove chips, fines and slime from the sump, filters, flumes and mist collectors with brushes and shovels, not by hand (HSE MW3, 2021).
Charge the system cleaner at the dose in the supplier's instruction and circulate it through all lines for the time stated there, opening valves where needed (UKLA, 2025).
Drain the cleaner and inspect bottlenecks, dead legs, hoses and connections for remaining sludge (UKLA, 2025).
Rinse until the final rinse pH equals the pH of the fresh water (Quaker Houghton, 2019).
Recharge straight away, since a cleaned machine left empty over a shutdown can flash rust (Quaker Houghton, 2019).
How long should system cleaner circulate in a coolant changeover?
Circulate the cleaner for the supplier's stated time for that product and that system, and quote that time in the procedure with its source. HSE's sump cleaning sheet sets no single figure; it tells shops to check the supplier's recommendation of system cleaner and circulation times (HSE MW3, 2021). Published supplier figures run from 1 hour to 24 hours, as the comparison below shows, so a number copied from another supplier's sheet can be off by a factor of several.
The table compares the circulation times two suppliers publish and the condition each one attaches.
Source | System | Cleaner dose | Circulation time |
|---|---|---|---|
Quaker Houghton | Single sumps or central systems, cleaner or coolant in fresh water | Safe and effective concentration for the product | 8-24 hours (Quaker Houghton, 2019) |
Dubois Chemicals | Central system | 3% PERKLEEN 1225 | At least 2-4 hours or until clean (Dubois Chemicals, 2020) |
Dubois Chemicals | Individual machines | 2% PERKLEEN 1225 | 1-8 hours by severity of soils (Dubois Chemicals, 2020) |
Each row holds only for that supplier's cleaner: the Dubois rows are for its PERKLEEN 1225, where individual machines run 1-8 hours at 2%, longer for heavily soiled sumps (Dubois Chemicals, 2020).
Write down the end point as well as the time, for example "until lines and sump are free of slime". In the Dubois central system instruction, cleanliness, not the clock, decides when to stop.
Why do coolant suppliers give different cleaner circulation times?
The times differ because each instruction describes different cleaners, system sizes and starting conditions. It does not mean one supplier is wrong. The Quaker Houghton guide covers a full dump, clean and recharge of single sumps or central systems with time and capacity to spare, and runs a cleaner or coolant for 8-24 hours (Quaker Houghton, 2019). Dubois Chemicals ties its time to one cleaner product, treats central systems and individual machines separately, and lets soil severity set the time between 1 and 8 hours (Dubois Chemicals, 2020). Chemistry matters too. Quaker Houghton notes that a higher pH cleaner is often more aggressive and may work more quickly, but can cause skin problems and stain some aluminum grades.
Rinse practice differs in the same way. Quaker Houghton rinses with fresh water, Dubois refills individual machines with a 1.0% coolant concentration to carry out cleaner traces, and the UKLA guide flushes with a top-up dilution of coolant and states that plain water should not be used because of potential corrosion of metal surfaces (UKLA, 2025). So a procedure written for one customer should name one cleaner, one supplier instruction and one rinse medium, and it should not mix values from different sheets.
How do you set the initial concentration and checks after a coolant recharge?
Mix concentrate into water at the supplier's target, then confirm the result with a refractometer: multiply its reading by the product's factor, the adjustment figure that belongs to that coolant. Quaker Houghton has the water quality checked first, since high hardness or chlorides can make dilutions unstable, and recommends a premix unit with the concentrate added to the water, "Oil In Last" (Quaker Houghton, 2019).
The UKLA guide explains why the factor matters: a refractometer reading is not a direct measure of concentration, product-specific factors must be applied, and the instrument is calibrated to zero on the mix water at about 20 °C (UKLA, 2025).
Dubois Chemicals checks concentration and pH after the new charge has circulated for 30 minutes in a central system (Dubois Chemicals, 2020). Keep the pH within the supplier's recommended range, because the UKLA guide links a falling pH to corrosion and microbial growth and a rising pH to skin irritation.
After that, HSE recommends weekly refractometer and pH readings (HSE MW5, 2021) and a dipslide test about a week after refill, with use continuing below 10,000 CFU/ml (HSE MW3, 2021). Before production restarts, Quaker Houghton lists filters in place, automatic lubrication back on, nozzles aligned and supplemental equipment such as chillers and skimmers running.
What should operators be told after a coolant changeover?
Tell operators which fluid is now in the machine, how to test it and top it up, and what to report. Quaker Houghton's guide says that when a new fluid is introduced, its testing methods should be approved and communicated, operators should be trained before the change, labeling should be updated, and the correct fluid must be used as makeup from then on, because incompatible fluids can cause serious problems (Quaker Houghton, 2019). The same guide warns operators that foaming or odor are possible while cleaners run.
A one-page operator notice can carry five items: the product name and its refractometer factor, the target concentration and pH range from the supplier, the makeup fluid and its dilution, the check frequency, and the date of the dipslide test. HSE's leaflet for employees adds what operators should report: layers of scum or large amounts of tramp oil on the sump, or sump fluid that is dirty or smelly (HSE INDG365, 2006). Post the notice at the machine and keep a copy with the customer's changeover record. Whoever tops up the sump next then uses the same factor and target as the person who recharged it.
How do you check a coolant changeover procedure before it goes to the customer?
Before the procedure goes to the customer, check each step's safety duty, source value and record against the table below. The table catches the common mistakes: a circulation time copied from another supplier, a refractometer reading logged without the product factor, a cleanout timed before a weekend shutdown, and open questions left in the customer's copy.
Use it to decide whether the written procedure is ready to send, or what to fix first.
Check | Pass | Fail and what to do |
|---|---|---|
Lockout and SDS in the steps | Each hands-on step names lockout and the SDS PPE (OSHA, 29 CFR 1910.147, 2026) | Rewrite the step; a separate safety page is not read at the sump |
Cleaner and circulation time | Product, dose and time quoted from one supplier instruction (HSE MW3, 2021) | Replace mixed values with the supplier's own |
Sump, filters, lines | Free of chips and slime before recharge | Add a manual cleaning step with tools |
Rinse | Final rinse pH equals fresh water pH (Quaker Houghton, 2019) | Rinse again before recharge |
Initial concentration | Refractometer reading times product factor (UKLA, 2025) | Record the factor and recalculate |
First week records | Concentration, pH and dipslide date logged | Add the record sheet to the procedure |
Operator notice | Issued and posted at the machine | Write and post it before restart |
The row most exposed to error is likely the circulation time, since it is the number most easily copied from the wrong sheet.
Questions the shop and supplier have not settled, such as a waste contractor not yet confirmed, belong in the internal file, not in the procedure the customer signs. The guide on what to leave out of a customer technical report covers that line in more detail.
Lubinpla's document writing can turn a case into this kind of usage guide: it carries over only the changeover conclusions settled in the conversation, leaves open items out, and files the approved document to the customer account as a PDF.
Frequently asked questions
Can you add system cleaner to the old coolant instead of draining first?
Adding cleaner to the old coolant in a running machine is an accepted alternative in Dubois Chemicals' instruction at 1.0-3.0% of system volume, with pH checked so it does not rise above 10, which could cause skin problems (Dubois Chemicals, 2020). Quaker Houghton notes that the shortcut saves time but can reduce cleaner effectiveness.
Does every coolant changeover need a biocide run?
A biocide run is not needed in every coolant changeover. Quaker Houghton says the step may not be necessary if the microbiological situation is under control, and HSE advises adding biocide only after good fluid management has been tried, at the supplier's dose (HSE MW5, 2021).
What changes when the new coolant is a different type?
Changing coolant type adds a risk: residue from the previous product. Quaker Houghton gives the example of switching from a solution synthetic to a soluble oil, where built-up residue could lead to an unstable emulsion, so the cleaning step deserves extra time and inspection (Quaker Houghton, 2019).