What a water treatment proposal to a plant should include
Summary
A water treatment program proposal for a plant needs six sections: current condition, control targets, chemicals and feed, test schedule, reporting, and plant duties. Whether the program covers a cooling tower, a closed loop or a boiler, each target needs a range with its source, and each test needs a frequency and a named person who runs it.
One university RFP for a central utility plant asks bidders for corrosion coupon testing on a 90-day basis for tower, closed loop and steam condensate systems, with data reported within 30 days (University of Arizona, 2026).
The same RFP sets on-site service at no less than two hours per plant per week and a written report at every service call (University of Arizona, 2026).
ANSI/ASHRAE Standard 188-2021 establishes minimum legionellosis risk management requirements for building water systems; the 2021 edition replaced permissive language with enforceable language (ASHRAE, 2021).
HSE's HSG274 Part 1, second edition published March 2024, covers what a cooling water treatment programme requires in the UK (HSE, 2024).
This structure fits a supplier's proposal to an industrial or campus plant for cooling tower, closed loop and boiler water treatment. It is not the plant's own Legionella program, and it does not set boiler chemistry limits. Pricing and equipment terms, such as a cost per 1,000 gallons and controller leasing, go in a separate commercial section outside this structure (University of Arizona, 2026).
What do you need before writing a water treatment program proposal?
A water treatment program proposal starts from system data, gathered before any text is written: each system's volume, make-up rate and cycles of concentration, a recent analysis of the make-up water, the chemicals in use, the feed and control equipment, and the plant's problem history.
An owner who issues a request for proposal (RFP) often supplies part of this. One university RFP for central utility plants gives bidders the cooling tower make-up per year, the cycles of concentration (4.0 cycles) and the system volume (300,000 gallons), and the boiler steam per year and cycles of concentration (50.0 cycles) (University of Arizona, 2026).
Without an RFP, the supplier collects the same facts on a site survey. The New Jersey Department of Health water management program template, based on ASHRAE Standard 188, lists what a cooling tower description should record: purpose, number of cells, total nominal tonnage, total water volume, equipment type, whether treatment is manual or automated, and the names of the oxidizing and non-oxidizing biocides (NJDOH template). Ask as well for the plant's discharge limits and its existing water management program, because both constrain the targets.
What should the current-condition section of a water treatment proposal show?
The current-condition section of a water treatment proposal shows a dated water analysis for every stream the program will treat, the condition of the equipment, the current treatment and its results, and a dated problem history. The plant will later hold the program against this baseline to judge whether it worked.
List each stream on its own. One RFP's minimum test list names raw water, softened water, tower water, chilled water, RO water, boiler feedwater, steam boiler water and condensate, each with its own parameters; tower water alone has fourteen, from pH, conductivity and ORP to azole, iron, copper and free halogen (University of Arizona, 2026).
Mark where each number came from: the supplier's own test on a given date, the plant's log, or an outside lab. State the inputs behind any scale prediction, too. The same RFP asks bidders to note the skin temperatures used in calculating saturation indices (University of Arizona, 2026).
For the problem history, write one line per event: the date, the system, what was found (scale, corrosion, a high bacteria count, a failed coupon), what was done, and whether the problem came back. Keep any claim about cause apart from what was observed.
How do you set control targets and ranges in a water treatment proposal?
A water treatment proposal sets control targets per parameter. For each one, state the control location, the range, how and how often it is monitored, who monitors it, and the corrective action when the value leaves the range. Those are the columns of the control measures table in the New Jersey water management program template (NJDOH template).
That template gives example cooling tower limits: free available chlorine above 0.5 ppm, total chlorine or bromine above 1 ppm, conductivity below 1200 micromhos/cm and pH 7 to 9, each checked three times a week by engineering staff (NJDOH template). The department calls its recommendations minimum requirements and says they are "merely considered examples". A proposal therefore copies the structure, not the numbers.
Name the source of every range. For Legionella control in cooling towers, the range comes from the plant's water management program under ANSI/ASHRAE Standard 188-2021 in the United States (ASHRAE, 2021), or from HSG274 Part 1 in the UK (HSE, 2024). Boiler ranges come from the boiler maker's limits or from ASME CRTD Vol. 34, whose stated aim is minimizing "the penalties of severe corrosion or deposition, frequent cleaning requirements, or unscheduled outages in steam generator systems" (ASME CRTD Vol. 34). For discharge, the plant's permit sets it.
Which chemicals and feed methods should a water treatment proposal name?
For each system, a water treatment proposal names every product by function and active ingredient, with its target dose as a minimum and a maximum, the feed point, the feed control method, the container type and the dosing schedule. One RFP puts the request plainly: "Provide the minimum/maximum levels in PPM; active ingredients; container sizes, materials, and types; and recommended dosage schedules in days" (University of Arizona, 2026).
Feed control matters as much as the product. The same RFP specifies stabilized bromine fed three times per week to reach a free halogen residual of 1 ppm at the end of a four-hour feed, with halogen feed controlled by time and ORP differential, and a glutaraldehyde shot above 120 ppm once per week (University of Arizona, 2026). If a proposal names a biocide but not what triggers its feed, the plant cannot check it.
Commit to a safety data sheet (SDS) for every product. Under US OSHA 29 CFR 1910.1200(g)(7)(i), distributors must provide safety data sheets with the initial shipment and with the first shipment after an update (OSHA, 29 CFR 1910.1200). Where acids or oxidizing biocides are fed, point to each product's SDS for storage and handling rather than restating it.
Which tests and test frequencies belong in a water treatment program proposal?
A water treatment program proposal lists every test with the person who runs it and how often, split three ways: the plant's routine tests, the supplier's service-visit tests, and periodic studies such as corrosion coupons. One RFP asks bidders for exactly this: "a list of tests to be performed during each service visit, a calendar of services to be performed during the year, and a list of tests to be run by UA personnel per day" (University of Arizona, 2026).
The table shows how one owner's RFP and one public template split common tests by person and frequency.
Test | Who runs it | How often |
|---|---|---|
Free or total halogen, conductivity, pH in the tower | Plant engineering staff | 3 times a week (NJDOH template) |
Dip slide total bacteria, open and closed systems | Plant staff, supplied by the vendor | Weekly (University of Arizona, 2026) |
Service visit test set and own-reagent check of plant results | Supplier | Each weekly visit (University of Arizona, 2026) |
Chilled water microbiological quality | Supplier | At least quarterly (University of Arizona, 2026) |
Corrosion coupons, tower, closed loop and condensate | Supplier | 90 days, reported within 30 days (University of Arizona, 2026) |
Boiler feedwater dissolved oxygen | Supplier | At least annually (University of Arizona, 2026) |
The coupon row is the one most often left vague: in that RFP, coupons run year-round on a 90-day basis using the plant's actual metallurgies, and the data must be reported within 30 days (University of Arizona, 2026).
What should the plant do under a water treatment program, and what does the supplier do?
Under a water treatment program, the plant runs the routine daily and weekly tests, keeps the logs, operates the equipment and acts on alarms. The supplier sets the chemistry, verifies the plant's results, services the feed equipment, reports and trains.
One RFP spells out the supplier side. Service means "the field testing and immediate correction and/or adjustment of chemistry as needed of all treated systems, the review of written and computerized log sheets, inventory review, the inspection of chemical feed equipment, and general equipment inspections", with a written report at every service call and verbal and written notice to the plant supervisor of any deviation (University of Arizona, 2026). The supplier also trains plant personnel on the program and on spill response for the supplied chemistry (University of Arizona, 2026).
On the plant side, the same RFP has plant personnel inoculate bacteria strips 48 hours before the service visit and log the supplier's on-site time (University of Arizona, 2026).
Reporting closes the loop. In the proposal, name the report per service visit, who receives it, the deviation notice and its timing, and what each quarterly review covers, such as chemical usage, water usage, coupon results and out-of-control exceptions (University of Arizona, 2026). For what the written service report to the plant should leave out, see the guide on what to leave out of a customer technical report.
The plant's water management program team, which may include a water treatment specialist, keeps ownership of the Legionella program itself (NJDOH template).
How do you check a water treatment program proposal before sending it?
Read each of the six sections against what it must state, and ask what the plant could not enforce if that section were missing. A proposal passes when every range has a source, every test has a person and a frequency, and every duty has an owner.
Use the check table to decide whether the proposal is complete enough for the plant to approve and to hold the supplier to.
Proposal section | What it must state | If missing |
|---|---|---|
Current condition and problems | Dated analysis per stream, equipment condition, current treatment, problem history | No baseline to judge results against |
Control targets and ranges | Parameter, location, range and its source, monitoring, corrective action | Ranges cannot be defended or enforced |
Chemicals and feed method | Function, active ingredient, min and max dose, feed point and control, SDS | Plant cannot check dosing or handle products safely |
Tests and frequency | Test, who runs it, how often, coupon schedule and reporting time | Gaps in monitoring nobody owns |
Reporting | Report per visit, deviation notice, periodic review content | Problems found late |
Plant duties | Daily tests, logs, equipment operation, access | Disputes over who missed a task |
Control targets carry the most weight. A range without its source is the gap a plant engineer finds first.
Lubinpla is an applied AI company whose document drafting builds a proposal like this from your own records and site history first, then from public sources. It asks once, only for facts neither holds, and returns one cited document for your review.
Common mistakes in water treatment program proposals
The mistakes that come up most are ranges copied from another plant, tests with no owner, and control limits with no corrective action.
Copying example limits as targets. Template numbers, such as those in the New Jersey template, are stated as examples (NJDOH template). The proposal's ranges should come from this plant's program, equipment and permit.
Listing tests without a frequency or an owner.
Leaving out corrective action. Every limit needs an action for when the value is out of range, and a person who takes it.
Treating the proposal as the Legionella program. The plant's water management program under ANSI/ASHRAE Standard 188-2021 is the plant's document (ASHRAE, 2021); the treatment proposal supports it.
Leaving out the timing of coupons and periodic studies. State the exposure period and the reporting deadline.
Leaving equipment ownership vague. Name who owns, maintains and removes each controller, pump and tank.
Frequently asked questions
Does a water treatment proposal replace the plant's water management program?
No. A Legionella water management program is the plant's own document, developed and maintained by its program team (NJDOH template). The supplier's proposal should match its control limits and monitoring to that program, and say which tasks the supplier carries out for it.
Should safety data sheets be attached to the proposal?
Follow the owner's request. One RFP tells bidders not to submit SDSs with the bid and says the owner will request them as needed (University of Arizona, 2026). In the United States, distributors must still supply SDSs with the first shipment of each hazardous product (OSHA, 29 CFR 1910.1200).
How often should the program be reviewed with the plant?
Agree on a review interval in the proposal. One RFP requires quarterly review meetings covering chemical usage, water usage, corrosion coupon results and out-of-control exceptions by system (University of Arizona, 2026). The New Jersey template calls for at least an annual review of the water management program (NJDOH template).
Where do UK plants find the cooling water treatment requirements?
UK plants use HSE's Legionnaires' disease technical guidance, HSG274. Part 1 covers evaporative cooling systems, including the requirements of a cooling water treatment programme and water quality monitoring, and its second edition was published in March 2024 (HSE, 2024).